A reorder point tells you when to order the next batch. Estimate issues expected before replenishment and add safety stock for delays or urgent replacements. Calculate separately for groups of interchangeable configurations.

Review recent issues by hardware standard. Distinguish hires from failures and planned replacements. Check confirmed hiring plans: a weekly average can conceal a one-off office opening.
Supplier shipping time does not necessarily include tagging, configuration or IT acceptance. Measure from order placement until a complete, working kit can be issued.
Multiply expected weekly issues by replenishment lead time in weeks, then add agreed safety stock. Compare that threshold with unreserved ready stock plus confirmed deliveries due in time. Subtract reservations only once. Exclude known hires already covered by reservations from the forecast of additional demand.
Assign someone to review inventory and someone to approve purchases. Agree the review interval. If reviews are weekly, allow for demand until the next review as well. Compare actual replenishment times with assumptions after several deliveries and adjust the buffer.
| Measure | Calculation |
|---|---|
| Inventory position | Free, ready-to-issue laptops plus confirmed deliveries available in time. |
| Reorder point | Lead-time demand plus safety stock. |
| Exception | Schedule a large planned hiring intake separately. |
Stock is reviewed daily. Four additional issues per week over a two-week lead time, plus three spare units, give a reorder point of 4 × 2 + 3 = 11. Four of 14 ready units are reserved, leaving 10 free. With nothing on order, replenish now. If six confirmed units arrive before they are needed, the position is 16. Monitor the delivery date instead of placing a duplicate order.